Capacity-based RFP approved by the Georgia Public Service Commission as part of Georgia Power's 2022 Integrated Resource Plan. Procurement targets 500 MW with a minimum storage duration of 2 hours. RFP includes: (i) Standalone ESS with grid charging capability; and (ii) ESS with Renewable Resource and grid charging capability. RFP issuance date: Friday, January 23, 2026. Bid due date: Tuesday, March 3, 2026. Targeted earliest Commercial Operations Date (COD): 2028. Targeted latest COD: 2031. Short List and Reserve List determined December 2026. Contract execution and certification period: January-July 2027.