2025 Summer Indexed Wind, Solar, Brownfield, and Hydropower REC RFP (AIC, ComEd, and MEC)
Illinois Power Agency is procuring 5.2M indexed RECs annually from new utility-scale wind and hydropower projects (over 5 MW), 666K RECs from new utility-scale solar (over 5 MW), and 222K RECs from brownfield photovoltaic through August 1, 2025, with 20-year contracts indexed to real-time locational marginal prices at MISO-IL Hub or PJM-NIHUB. RECs are allocated across Ameren Illinois (27%), ComEd (73%), and MidAmerican Energy (0.2%), with projects required to deliver first RECs by May 31, 2030. Part 1 proposals due June 30, 2025.
Categories
Important dates
-
Published
-
Submission deadline
Deadline passed
AI overview
The Illinois Power Agency (IPA) conducted a competitive procurement for indexed renewable energy credits (RECs) from new utility-scale wind projects (over 5 MW), new utility-scale solar projects (over 5 MW), new brownfield site photovoltaic projects, and new or modernized/retooled hydropower projects at existing dams. This procurement was conducted under Public Act 102-0662 (Climate and Equitable Jobs Act) and Public Act 103-0380 (hydropower provisions), in accordance with the IPA's 2024 Long-Term Renewable Resources Procurement Plan approved by the Illinois Commerce Commission on February 20, 2024.
The procurement targeted 5,243,684 RECs delivered annually from either new utility-scale wind or hydropower projects, 666,666 RECs delivered annually from new utility-scale solar projects, and 222,000 RECs delivered annually from new brownfield site photovoltaic projects. RECs from selected projects were allocated to three utilities in specified proportions: 27.09% to Ameren Illinois Company (AIC), 72.67% to Commonwealth Edison Company (ComEd), and 0.24% to MidAmerican Energy Company (MEC). Winners entered into 20-year indexed REC contracts with indexed pricing mechanisms tied to real-time locational marginal prices at either MISO-IL Hub or PJM-NIHUB, depending on bidder selection.
Key dates included: Part 1 Proposal deadline of June 30, 2025 at 12:00 PM CDT; Part 2 Proposal and bid assurance collateral deadline of July 23, 2025 at 12:00 PM CDT; Bid Date of August 1, 2025; and Illinois Commerce Commission decision on August 7, 2025. Performance assurance was required to be posted by August 28, 2025. All projects were required to have achieved first REC delivery by May 31, 2030 (extendable to May 31, 2032 under certain conditions).
The procurement included requirements for Minimum Equity Standard compliance (14% of project workforce must consist of Equity Eligible Persons or Contractors for projects with Date of First Operation on or after December 15, 2022). Bidders could optionally commit to higher equity levels (above 14%) for strike price reductions during bid evaluation. Energy Transition Community Grant Area projects and certain hydropower projects in preference communities received evaluation prioritization.
Resources & contact
Proposal Document
View proposal documentUnlock Full Access to Utility Proposals
You're viewing past opportunities. Start a free trial to see active RFPs right now, filter by your utilities, and get real-time alerts — no credit card required.
Already have an account? Log in