COA - SW Substation - C401 Perimeter Wall
Design, fabrication, and installation of 15-foot precast concrete perimeter wall with motor-operated gates for City of Anaheim Southwest Substation security upgrade; proposal deadline February 18, 2025.
Important Dates
Deadline
Deadline passed
Published
AI Overview
Burns & McDonnell is executing an upgrade to the City of Anaheim's Southwest Substation, with a key component being the construction of a new perimeter wall. The scope includes design, fabrication, and installation of new 15-foot-high precast concrete perimeter walls to replace existing 8-foot-high walls. The project also involves expanding the substation into newly acquired land and extending the perimeter. Motor-operated gates with integrated access control systems will be installed for site access. The goal is to improve substation security while implementing an architecturally styled design.
Important dates for this solicitation include a pre-proposal meeting on January 30, 2025, a questions and answers deadline of February 11, 2025, and a proposal submission deadline of February 18, 2025 at 01:00:36 UTC. Bidders must submit pricing proposals using the provided bid form and pricing breakdown form.
The project involves site logistics planning and coordination with specific technical specifications outlined in the attached RFQ documents. Geotechnical information is provided to support design and planning efforts. Bidders must be qualified to handle precast concrete wall fabrication and installation, including motor-operated gate systems with access control integration.
Submission instructions require bidders to complete all required forms including the Bidder Questionnaire, Bid Form, and Bid Pricing Breakdown Form. Technical specifications and site plans are provided in the attached documents, including geotechnical reports and construction administration controls.
Resources & Contact
Posting URL
View Original Posting