Southern California Edison Company (SCE) issues this Local Capacity Requirements Request for Offers (LCR RFO) for incremental capacity in the West LA Basin and Moorpark Sub-Areas. Products solicited include Gas Fired Generation, Combined Heat and Power, Demand Response, Energy Efficiency, Energy Storage, Renewable, Resource Adequacy, and Distributed Generation. SCE is authorized to procure 1400 to 1800 MWs of new resources in the Western Los Angeles Basin sub-area and 215 to 290 MWs in the Moorpark sub-area to meet LCR needs by 2021. The delivery period for projects connected to Goleta, Johanna or Santiago High Voltage substations must start delivering between 1/1/2015 to 1/1/2021. The delivery period for all other projects in the Western Los Angeles Basin or Moorpark sub-areas must start delivering between 1/1/2018 to 1/1/2021. All projects must include the entire calendar year of 2021 in their delivery period.