Unknown
RFP

Pre-Bid Meeting Q&A

Jamaica's Generation Procurement Entity seeks developers to build, own, and operate up to 100 MW of renewable energy generation capacity on a Build-Own-Operate basis, with individual awards capped at 50 MW net. Bidders must fund and execute interconnection feasibility studies with Jamaica Public Service, cover all network upgrade costs, and submit executed or pending land leases, independent yield assessments, and technical specifications. Maximum award per developer is 50 MW; alternative capacity bids for the same site are treated as mutually exclusive.

Generation Procurement Entity (GPE), Jamaica JM
Categories:
Power purchase agreements (PPAs) Renewable energy procurement Independent power producer (IPP) contracts Interconnection studies

Important Dates

Deadline

Unknown

Published

AI Overview

This Request for Proposals seeks qualified bidders to develop, finance, build, own, and operate renewable energy generation facilities with a capacity of up to 100 MW (net) on a Build, Own and Operate basis. The GPE (Generation Procurement Entity) is procuring electricity generation capacity from renewable energy resources to meet energy demand objectives. Bidders are required to undertake their own interconnection feasibility studies with the Jamaica Public Service (JPS) transmission system and provide detailed project interconnection schedules showing costs to interconnect at both distribution and transmission levels. The project scope includes all aspects of plant design, construction, operation, and maintenance, with bidders responsible for all interconnection costs and any necessary network upgrades.

Key requirements include submission of executed or evidence of pending lease agreements for project land, detailed interconnection feasibility studies, yield assessments conducted by independent engineers with arm's length relationships to the bidder, comprehensive technical specifications, and bid bonds equivalent to the offered net capacity. Bidders may submit alternative bids for the same project site with different capacity offerings and prices, which will be treated as mutually exclusive proposals. Maximum award per bidder is limited to 50 MW net capacity. All submission materials must be delivered in physical form (paper copies and USB flash drive with digital content) in person at GPE premises; email or postal submissions will not be accepted.

Key dates include a Pre-Bid Meeting held on March 18, 2024 with Questions and Answers documentation provided. The RFP document number is 2023-18-09-GPE-RFP.001. Evaluation criteria include technical feasibility, interconnection requirements, financial viability, equipment sizing optimization, environmental compliance, and grid impact assessment. The procurement process includes feasibility study review during evaluation, with grid impact studies to be conducted after bid award and not included in evaluation. Clarification documents have been published on the GPE website addressing technical questions from prospective bidders regarding interconnection points, upgrade costs, bond requirements, and consortium structures.

Resources & Contact

Other open RFPs in this category

Active opportunities related to this one. Sign up for alerts to track new ones automatically.

1 days left
Jun 4, 2026

TVA – 2026 Existing Generation Resource Capacity RFP — Tennessee Valley Authority (TVA)

2 days left
Jun 5, 2026

Southern Spirit DC Tie Interconnection Study — ERCOT

2 days left
Jun 5, 2026 3:00 PM

2026 Renewable Energy Resource Acquisition — Colorado Springs Utilities

5 days left
Jun 8, 2026 7:00 PM

Solar and Energy Storage Feasibility Across Municipal Facilities — City of Pasadena

5 days left
Jun 8, 2026 9:00 PM

Design-Build Services for a Hydrogen Fueling Station — City of Pasadena - Public Works Department, Engineering